Mobile Plant

Mobile Package Plant Room
Client: Cofely District Heating
Completion date: June 2012

Project Information

Design and install three self-contained mobile packaged plant rooms for support to the Energy Centre for the Olympic Games 2012.

Installation
  • 2 No. 2mw Wellman Ygnette boilers with duel fuel burners.
  • 1 No. 1.25 Wellman Ygnette boilers with duel fuel burner
  • 3 No. AVK-SEG Generators
  • 3 No. 4800ltr bunded oil tanks
  • Trend IQ view 4 control system
  • 3 No. Pressurisation Units
  • 12 No. Lowara inverter pumps
  • DSEAR compliant